Tunnel it down
- Mic Up
- Sep 3, 2020
- 4 min read
Image Source: Construction Week Online
The 9-km-long Atal tunnel under the Pir Panjal range, named after former Prime
Minister Atal Bihari Vajpayee, will be the world’s longest highway tunnel above the altitude
of 10,000 feet (3000 metres). It was scheduled to be completed by May 2020, in a revised
estimate, but the Covid-19 pandemic pushed back the completion by a few months due to
lockdown conditions. Official sources said the tunnel had missed its February 2015 deadline
owing to tough geographical conditions in the Himalayas along with harsh climatic
conditions, besides a limited working season of six months in the tunnel's north portal and
missed it yet another time in 2019 and has finally been completed.
A feasibility study of the project Rohtang Tunnel was carried out in M
ay 1990 following
which the geological report was submitted in June 2004. This was followed by a design and
specification report which was prepared and finalized in December 2006. Border Roads
Organisation (BRO) officials say the project received final technical approval in 2003.
Following approval by Cabinet Committee on Security in 2005, tenders were floated in 2007
and the foundation stone was laid in July 2010 by UPA chairperson Sonia Gandhi. The
project was scheduled to be completed by February 2015 but it got delayed due to
unexpected problems.

It was originally designed to be 8.8 km long but GPS readings taken
on completion show it to be 9 km long.
The project was being built by the Border Roads Organisation (BRO), a wing of the Defense
Ministry, in collaboration with Afcons, a joint venture with Strabag AG.
Taming the glacial-fed Seri rivulet was a challenge for the engineers. It's a tributary of the
Beas river and the tunnel alignment is crossing beneath the rivulet. However, a geological
surprise in the form of a rivulet that sprung up in 2012 during the tunnel digging posed a
challenge. Its torrential inflow was emerging into the tunnel.
Once encountering the Seri rivulet's impact in 562 metre area. They have managed to
reduce its impact to just 30 metres by 2018 and had been working on controlling its seepage
thereafter. The construction teams faced fast flowing water from Seri Nullah, which flowed
on top of the tunnel route and impeded construction efforts. The sheer volume of water
prevented construction for several months while project engineers grappled with a way to
tackle the problem. The rock structures faced by the engineers too caused impediments.
The south portal of the tunnel had schist, migmatites and phyllite rocks while the north
portal had incoherently folded gneiss and biotite schist which were brittle and ductile in
nature which not only compromise the aesthetics of the tunnel but also would have been
instrumental in putting entire structure under the danger of a collapse.
The tunnel, whose both ends can be accessed after negotiating 20 landslide and snow
avalanche zones, is located at altitudes ranging above 3,000 metres and lies beneath the
snow covered Rohtang Pass, whose 70 per cent of the top remains under snow even during
summer.
The unique features of this tunnel begin a fair distance away from it on the approach roads
to the north and south portals. Bridges in rivers on the approach to the tunnel from both
the portals have also been completed and are now being painted. Snow galleries have also
been built at the approach road to the tunnel from Manali side, and this will ensure all-
weather connectivity.
Other features include an emergency escape tunnel under the main tunnel. This would
provide an emergency exit in case of any untoward incident which may render the main
tunnel unusable. The tunnel also provides a telephone every 150 metres, fire hydrant every
60 metres, emergency exit every 500 metres, turning cavern every 2.2 km, air quality
monitoring every one km, broadcasting system and automatic incident detection system
with CCTV cameras every 250 metres. BRO officials say vehicles will travel at a maximum
speed of 80 km per hour. Up to 1,500 trucks and 3,000 cars are expected to use it per day
when the situation gets to normal post Covid-19 restrictions. The strategic importance of
the Manali-Leh link was realized by the Indian government almost a decade ago
when Pakistan tried to cut off the Srinagar-Leh road during the Kargil conflict, in a bid to
restrict road access to Ladakh.
Currently, the movement of armed forces to the forward areas in Ladakh from Manali side,
which doesn't fall in the firing range of Pakistan forces, is feasible only from June to mid-
December.
The completion of the Rohtang tunnel is a key element in the Defence Ministry's attempts
to make the entire 475 km-long Manali-Keylong-Leh highway, used by the armed forces to
reach forward areas in Ladakh bordering China and Pakistan, motor able round the year,
said officials.
Cutting through the Pir Panjal range, the tunnel will reduce the distance between Manali
and Leh by 46 km. The Rohtang Pass, to which the tunnel provides an alternate, is located at
a height of 13,050 feet, and a journey from Manali Valley to Lahaul and Spiti Valley, which
normally takes around five hours to negotiate, would now be completed in little over ten
minutes.
While the tunnel will be a boon to the residents of the Lahaul and Spiti Valley who remain
cut off from the rest of the country in winters for nearly six months due to heavy snowfall,
the tunnel will provide almost all-weather connectivity to the troops stationed in Ladakh.
However, for full all-weather connectivity, additional tunnels will have to be built on the
Manali-Leh route so that the high passes on the axis do not impede movement due to
snowfall. A 13.2 km long tunnel will have to be built to negotiate the 16,040 feet high
Baralacha pass and another 14.78 km long tunnel will be required at the Lachung La pass at
16,800 feet. A third 7.32 km long tunnel will be required at Tanglang La pass at 17,480 feet.
This project has been welcomed by the people living in the addressed area as they have
dreaded the slow development and continued isolation due to unavoidable climatological
and topographical conditions.
NISHITA PATIL
Comments